A pre-handover checklist for office IT fit-outs

The gap between "installation complete" and "actually usable on Monday" is a specific list of items. This is the one we work through before we hand a site over.

5 May 20264 min read
A pre-handover checklist for office IT fit-outs

Sign-off tends to happen when the visible work looks finished. But the things that cause a bad first week are mostly invisible: undocumented patching, an untested failover, a licence assigned to a departed contractor. Here is what we confirm before calling a site complete.

Documentation

  • As-built floor plan with outlet numbering that matches the physical labels
  • Patch schedule mapping every port to its outlet and switch
  • Certification results for every permanent link
  • Rack elevation, including power distribution and UPS capacity
  • Device inventory with serial numbers, warranty dates and firmware versions

Network

  • VLAN plan documented, with which devices belong where and why
  • DHCP scopes sized with headroom, reservations recorded
  • Internet failover actually tested by pulling the primary link
  • Wi-Fi validated by walking the floor, not by reading a planning tool
  • Guest network genuinely isolated from internal resources

Security and access

  • Default credentials changed on every device, including cameras and access controllers
  • Admin accounts assigned to named people, with a documented break-glass account
  • Backups running and — the part usually skipped — a restore tested
  • CCTV retention verified against the required number of days
  • Access control groups mapped to roles, with leavers already removed
A backup that has never been restored is a hypothesis, not a backup.

People

A short walkthrough with whoever will be first to notice a problem: reception, office management, the internal IT contact. Where the rack is, how to raise a ticket, what the escalation path looks like out of hours. Ten minutes here prevents most week-one calls.

And then a review date

Book a check-in about a month after occupancy. Real usage always reveals something the plan did not: a meeting room that is busier than expected, a printer in a dead spot, a department that grew. Fixing those while the project is fresh is far easier than raising them as new work six months later.